Salesforce Exam Business Analyst Topic 3 Question 38 Discussion

Actual exam question for Salesforce's Business Analyst exam
Question #: 38
Topic #: 3
[All Business Analyst Questions]

After stakeholders formally signed off on requirements, the business analyst (BA) received numerous emails requesting changes to Salesforce during uses acceptance testing (UAT). The BA quickly became overwhelmed by the requests and needs a way to organize and peritonitis them.

What should the BA use to help them organize these requests?

Show Suggested Answer Hide Answer
Suggested Answer: A

This answer states that change request log is what the BA should use to help them organize and prioritize requests for changes to Salesforce during UAT after receiving numerous emails from stakeholders who formally signed off on requirements. Change request log is a document or a file that records and tracks requests for changes to a project or a product, such as adding, modifying, or removing a feature or a functionality. Change request log is what the BA should use to help them organize and prioritize requests for changes to Salesforce during UAT because it helps the BA to manage and monitor the requests for changes, and to evaluate and approve or reject them based on their impact, urgency, or feasibility. Reference: https://trailhead.salesforce.com/en/content/learn/modules/salesforce-business-analyst-quick-look/use-stakeholder-engagement-skills


Contribute your Thoughts:

Tracie
6 months ago
Seriously, who would even consider the scope statement specification or the gap analysis document for this situation? The change request log is the clear winner here. Gotta keep those stakeholders happy, you know?
upvoted 0 times
Eun
5 months ago
B) Scope statement specification
upvoted 0 times
...
Celia
5 months ago
A) Change request log
upvoted 0 times
...
...
Francis
6 months ago
Yeah, a change request log makes sense to keep things organized.
upvoted 0 times
...
Nickolas
6 months ago
Hmm, this one seems pretty straightforward. The BA needs a way to keep everything organized, and the change request log is the way to go. Easy peasy.
upvoted 0 times
Barbra
5 months ago
B) Scope statement specification
upvoted 0 times
...
Annice
6 months ago
Definitely! The change request log will help the BA keep track of all the requests.
upvoted 0 times
...
Chaya
6 months ago
A) Change request log
upvoted 0 times
...
...
Grover
6 months ago
I'm going to have to go with option A. The change request log is designed specifically for situations like this where you need to manage and track all the changes coming in during UAT.
upvoted 0 times
Brynn
5 months ago
I agree, the change request log is the best option to organize and prioritize the requests during UAT.
upvoted 0 times
...
Desiree
5 months ago
C) Gap analysis document
upvoted 0 times
...
Gail
6 months ago
I think the change request log would be more suitable in this situation to manage the requests effectively.
upvoted 0 times
...
Marnie
6 months ago
B) Scope statement specification
upvoted 0 times
...
Lenna
6 months ago
That's a good choice. The change request log will definitely help the BA keep track of all the requests.
upvoted 0 times
...
Bettina
6 months ago
A) Change request log
upvoted 0 times
...
...
Cherry
7 months ago
The change request log sounds like the obvious choice here. It's the perfect tool to organize and prioritize all those incoming requests from the stakeholders.
upvoted 0 times
Rosalia
5 months ago
B) Scope statement specification
upvoted 0 times
...
Rosalia
6 months ago
A) Change request log
upvoted 0 times
...
Cyril
6 months ago
B) Scope statement specification
upvoted 0 times
...
Cyril
6 months ago
A) Change request log
upvoted 0 times
...
Audry
6 months ago
B) Scope statement specification
upvoted 0 times
...
Audry
6 months ago
A) Change request log
upvoted 0 times
...
...
Jennifer
7 months ago
Because it helps track and manage all the change requests.
upvoted 0 times
...
Brittney
7 months ago
Why do you think that?
upvoted 0 times
...
Jennifer
7 months ago
I think the BA should use a change request log.
upvoted 0 times
...
Lizbeth
7 months ago
I agree. Finding a way to prioritize those change requests is crucial.
upvoted 0 times
...
Francis
7 months ago
This question seems tricky to me.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77