Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Salesforce Exam CPQ Specialist Topic 5 Question 45 Discussion

Actual exam question for Salesforce's CPQ Specialist exam
Question #: 45
Topic #: 5
[All CPQ Specialist Questions]

A Quote has one Quote Line for a subscription product with an End Date that differs from the Quote's End Date.

Which date will CPQ use to calculate the prorate multiplier?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77