Who determines the tasks that are required to complete the committed backlog items in a Sprint?

Show Suggested Answer Hide Answer
Suggested Answer: A

A is correct because the Scrum team is the one that determines the tasks that are required to complete the committed backlog items in a Sprint. The Scrum team is a self-organizing and cross-functional group of people who work together to deliver a potentially releasable increment of the product at the end of each Sprint. The Scrum team breaks down the user stories into smaller and manageable tasks, and assigns them to the team members based on their skills and availability.


Contribute your Thoughts:

Alyce
5 months ago
The project manager? Really? This is Scrum, not some traditional project management approach. *chuckles*
upvoted 0 times
Camellia
3 months ago
Haha, yeah, the project manager doesn't have a say in Scrum.
upvoted 0 times
...
Ezekiel
3 months ago
That's right, the Product owner prioritizes the backlog items.
upvoted 0 times
...
Curtis
3 months ago
Exactly! The Scrum team determines the tasks.
upvoted 0 times
...
Omer
3 months ago
D) Project manager
upvoted 0 times
...
Aliza
3 months ago
C) Scrum master
upvoted 0 times
...
Paris
3 months ago
B) Product owner
upvoted 0 times
...
Grover
3 months ago
A) Scrum team
upvoted 0 times
...
Frank
4 months ago
C) Scrum master
upvoted 0 times
...
Laurel
4 months ago
B) Product owner
upvoted 0 times
...
Burma
5 months ago
A) Scrum team
upvoted 0 times
...
...
Devorah
5 months ago
It's gotta be the Scrum Master. They're the ones who keep the team on track and make sure the Scrum process is followed.
upvoted 0 times
Daron
5 months ago
Product owner
upvoted 0 times
...
Maurine
5 months ago
Scrum team
upvoted 0 times
...
...
Yoko
6 months ago
D) Project manager is not typically involved in Sprint tasks.
upvoted 0 times
...
Phyliss
6 months ago
Hmm, I'd say the Product Owner since they're responsible for the backlog and ensuring it's aligned with the Sprint goal.
upvoted 0 times
...
Marylou
6 months ago
C) Scrum master facilitates the process.
upvoted 0 times
...
Bettye
6 months ago
B) Product owner may provide input on priority.
upvoted 0 times
...
Tanesha
6 months ago
The Scrum team, of course! They're the ones who know the work best and can break down the tasks efficiently.
upvoted 0 times
Maia
5 months ago
Actually, it's the Scrum team that determines the tasks, not the Product owner.
upvoted 0 times
...
Billye
5 months ago
B) Product owner
upvoted 0 times
...
Dominga
5 months ago
Exactly! The Scrum team is responsible for determining the tasks needed to complete the backlog items.
upvoted 0 times
...
Zita
5 months ago
A) Scrum team
upvoted 0 times
...
...
Huey
6 months ago
A) Scrum team decides based on their expertise.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77