Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_ACTIVATE22 Topic 6 Question 19 Discussion

Actual exam question for SAP's C_ACTIVATE22 exam
Question #: 19
Topic #: 6
[All C_ACTIVATE22 Questions]

Which estimation technique can you use in an Agile delivery approach to size the user stories during sprint planning?

Show Suggested Answer Hide Answer
Suggested Answer: A

A is correct because Planning poker is an estimation technique that you can use in an Agile delivery approach to size the user stories during sprint planning. Planning poker is a game where each team member uses a set of cards with numbers that represent the relative effort of a user story. The team members reveal their cards simultaneously and discuss their estimates until they reach a consensus. This technique is based on the concept of story points, which are units of measure for expressing the overall effort required to fully implement a user story. Story points are assigned to user stories based on their complexity, risk, and uncertainty. Verified :

: Planning Poker


Contribute your Thoughts:

Pauline
5 months ago
Option C sounds like a lot of work, but hey, if the Product Owner wants to get their hands dirty, I'm all for it. Gotta love that attention to detail!
upvoted 0 times
...
Tracey
5 months ago
Yeah, I was thinking that too. D involves the entire team's best effort estimate.
upvoted 0 times
...
Sheldon
5 months ago
Haha, look at that, the Scrum Master trying to take over with option A. Nice try, but the team knows best when it comes to estimating user stories.
upvoted 0 times
...
Garry
5 months ago
Exactly, Agile is all about team collaboration. So, D - relative effort estimate by the project team, makes sense.
upvoted 0 times
...
Karina
5 months ago
I'm going with B. The Project Manager's relative effort estimate is the most reliable since they have the big-picture perspective on the project.
upvoted 0 times
Myra
5 months ago
True, their perspective can be valuable in estimating the effort needed for implementation.
upvoted 0 times
...
Irene
5 months ago
That makes sense. The Project Manager usually has a good overview of the project.
upvoted 0 times
...
Glendora
5 months ago
B) Project Manager's relative effort estimate that will be needed to implement and test the user story
upvoted 0 times
...
...
Terrilyn
5 months ago
Agree, A and C focus on individual roles too much. Scrum Master's detailed estimate doesn't fit Agile.
upvoted 0 times
...
Malcom
6 months ago
Yeah, method B seems off because it’s the project manager alone estimating.
upvoted 0 times
...
Margot
6 months ago
Option D is clearly the way to go. Relative effort estimates in Ideal Person Days are the gold standard for Agile sprint planning. The whole team's input is critical for an accurate assessment.
upvoted 0 times
Olene
4 months ago
I agree, it promotes collaboration and shared responsibility among team members.
upvoted 0 times
...
Lenna
4 months ago
D) Relative effort estimate in Ideal Person Days that reflects the best estimate by the project team
upvoted 0 times
...
Hailey
4 months ago
It ensures everyone's perspective is considered, leading to more realistic estimations.
upvoted 0 times
...
Malcolm
5 months ago
D) Relative effort estimate in Ideal Person Days that reflects the best estimate by the project team
upvoted 0 times
...
Willow
5 months ago
Absolutely, involving the whole team in estimating effort is key for accurate planning.
upvoted 0 times
...
Rolande
5 months ago
D) Relative effort estimate in Ideal Person Days that reflects the best estimate by the project team
upvoted 0 times
...
...
Pauline
6 months ago
I think the correct technique must involve the team, not just one person.
upvoted 0 times
...
Tracey
6 months ago
What do you think about the estimation techniques question?
upvoted 0 times
...
Alishia
6 months ago
I prefer A) Detailed top-down effort estimate by the Scrum Master, it helps in understanding the complexity of the user stories.
upvoted 0 times
...
Marcelle
6 months ago
That's true, breaking down each story into tasks can provide a more accurate estimate.
upvoted 0 times
...
Mary
6 months ago
I believe C) Detailed bottom-up effort estimate by the product owner is also a valid option for sizing user stories.
upvoted 0 times
...
Marcelle
6 months ago
I think the estimation technique you can use in Agile is D) Relative effort estimate in Ideal Person Days.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77