When loading master data for a material, you want to look at the new values before they are released for reporting. What could you do using modeling features? Note: There are 2 correct answers to this question.
I think A and D are the correct answers. Time-dependent attributes and enhanced master data update allow you to preview the changes before releasing them, right?
That's right. Selecting the 'Time Dependent' setting for material attributes and 'Enhanced Master data update' setting for material characteristic will help you view the new values before they are released.