You want to define time limits for change request processing according to duration and status based on the customerls KPIs. Which of the following actions will you perform? Note: There are3 correct answers to this question.
This question is a real 'change request' in itself! I'm just glad I don't have to process the time limits for it. A, C, and D sound like the winning combo though.
I think A, C, and D are the right answers here. Configuring process insight, using the generic time management BAdI, and setting up an SLA for change request types are key to defining time limits.
Jackie
6 months agoArlene
6 months agoAnnmarie
6 months agoAlba
6 months agoBritt
6 months agoKiley
6 months agoMinna
6 months agoGenevieve
6 months agoJohanna
6 months agoDell
6 months agoVirgina
6 months agoShenika
6 months agoStanford
6 months agoGracia
6 months agoAdaline
7 months agoMaile
6 months agoJunita
6 months agoReuben
6 months agoRosamond
7 months agoShawn
6 months agoCristy
6 months agoKris
6 months agoBenton
6 months agoDonette
7 months agoEveline
7 months agoVan
7 months agoPearlie
8 months agoErin
8 months ago