SAP Exam C_S43_2022 Topic 4 Question 27 Discussion

Actual exam question for SAP's C_S43_2022 exam
Question #: 27
Topic #: 4
[All C_S43_2022 Questions]

A Task List contains two operations:

* Every 3 MON: pump inspection

* Every 24 MON. pump replacement

When replacing the pump, the operation pump inspection will be ignored. How can you achieve this?

Show Suggested Answer Hide Answer
Suggested Answer: D

A cycle set sequence is a feature that allows you to combine several multiple counter plan cycles in a set and determine the order in which the system considers the cycle sets for scheduling.A multiple counter plan is a maintenance plan that is based on one or more performance-based or time-based cycles1.

In this case, you can create a cycle set sequence with two cycles:

Cycle 1: Every 3 MON: pump inspection

Cycle 2: Every 24 MON: pump replacement

You can assign a different maintenance item and task list to each cycle, and specify the repetition factor for each cycle. The repetition factor determines how many times the cycle is repeated before the next cycle in the sequence is considered. For example, if you set the repetition factor of cycle 1 to 8, the system will schedule the pump inspection 8 times before scheduling the pump replacement.

By creating a cycle set sequence, you can achieve the requirement that when replacing the pump, the operation pump inspection will be ignored. The system will only generate a call object for the maintenance item that is assigned to the current cycle set. Therefore, when the pump replacement is due, the system will not generate a call object for the pump inspection.

The other options are incorrect because:

Assign different hierarchy levels: Hierarchy levels are used to structure the task list operations into groups and subgroups. They do not affect the scheduling of the task list operations.

Set the lead float: Lead float is a time buffer that is added to the start or finish date of a task list operation. It does not affect the scheduling of the task list operations.

Create a task list hierarchy: A task list hierarchy is a structure that contains several task lists that are linked together by a superior task list. It does not affect the scheduling of the task list operations.

References:1: Cycle Set Sequence in Multiple Counter Plan - SAP Help Portal


Contribute your Thoughts:

Hildegarde
19 days ago
Option D is the bomb! Cycle set sequences are like the duct tape of task management - they fix everything!
upvoted 0 times
...
Maxima
21 days ago
Seriously, who needs to inspect the pump when you're just gonna replace it? D is the way to go, folks.
upvoted 0 times
Caitlin
5 hours ago
I think setting the lead float would also work.
upvoted 0 times
...
Mariann
3 days ago
Agreed, D is definitely the way to go.
upvoted 0 times
...
...
Mi
23 days ago
But wouldn't assigning different hierarchy levels also work?
upvoted 0 times
...
Estrella
23 days ago
D all the way! Gotta love those cycle set sequences. They make life so much easier.
upvoted 0 times
...
Celeste
25 days ago
I agree, D is the correct answer. Establishing a cycle set sequence is the best way to handle this scenario.
upvoted 0 times
Tracey
7 days ago
C) Create a task list hierarchy
upvoted 0 times
...
Pearlene
8 days ago
B) Set the lead float
upvoted 0 times
...
Antonette
14 days ago
A) Assign different hierarchy levels
upvoted 0 times
...
...
Stacey
28 days ago
I disagree, I believe the answer is C) Create a task list hierarchy.
upvoted 0 times
...
Mi
29 days ago
I think the answer is B) Set the lead float.
upvoted 0 times
...
Troy
1 months ago
Option D seems the way to go. Creating a cycle set sequence to replace the pump and ignore the inspection seems logical.
upvoted 0 times
Carmela
21 days ago
D) Create a cycle set sequence
upvoted 0 times
...
Martin
29 days ago
A) Assign different hierarchy levels
upvoted 0 times
...
...