SAP Exam C_TFG51_2211 Topic 5 Question 25 Discussion

Actual exam question for SAP's C_TFG51_2211 exam
Question #: 25
Topic #: 5
[All C_TFG51_2211 Questions]

You need to create a Corporate Calendar that allows for regional differences in standard work schedules. What details can the Corporate Calendar include? Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: A, D

Contribute your Thoughts:

Marjory
4 months ago
A and D, hands down. Gotta keep track of those regional holidays, am I right? Although, a good calendar should also include the mandatory company picnic. Can't forget that!
upvoted 0 times
...
Florinda
4 months ago
On-boarding and off-boarding activities? Seriously? That's HR's job, not the Corporate Calendar's.
upvoted 0 times
Darell
2 months ago
C) Core hours when workers are expected to be in the office, or on-site
upvoted 0 times
...
Darell
3 months ago
A) Specific non-working days
upvoted 0 times
...
...
Levi
4 months ago
Core hours are a must! How else will we know when to schedule all those pointless meetings?
upvoted 0 times
Carrol
2 months ago
B) On-boarding and off-boarding activities
upvoted 0 times
...
Lourdes
3 months ago
Yes, core hours are essential for scheduling meetings efficiently.
upvoted 0 times
...
Rebbecca
3 months ago
C) Core hours when workers are expected to be in the office, or on-site
upvoted 0 times
...
Elly
3 months ago
A) Specific non-working days
upvoted 0 times
...
...
Twana
4 months ago
I think core hours when workers are expected to be in the office should also be included for better coordination.
upvoted 0 times
...
Georgene
4 months ago
I believe on-boarding and off-boarding activities should be included as well.
upvoted 0 times
...
Mattie
4 months ago
I agree with Mitsue, it should also include recurring non-working days.
upvoted 0 times
...
Rashad
5 months ago
I think the Corporate Calendar should definitely include specific non-working days and recurring non-working days. That way everyone is on the same page about when the office is closed.
upvoted 0 times
Polly
4 months ago
C) Core hours when workers are expected to be in the office, or on-site
upvoted 0 times
...
Mary
4 months ago
D) Recurring non-working days
upvoted 0 times
...
Myra
4 months ago
A) Specific non-working days
upvoted 0 times
...
...
Mitsue
5 months ago
I think the Corporate Calendar can include specific non-working days.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77