New Year Sale ! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS412_2021 Topic 2 Question 27 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 27
Topic #: 2
[All C_TS412_2021 Questions]

Which statement regarding the creation of a new work breakdown structure (WBS element) are true?

Note : there are 3 correct answer for this question.

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Adolph
6 months ago
I agree with A, C, and D. The flexibility to have WBS elements serve multiple purposes is really handy. I once had a project where our WBS was so elaborate, it could have doubled as a Sudoku puzzle!
upvoted 0 times
Huey
5 months ago
Definitely, it's important to have that flexibility when creating a new work breakdown structure. It can make a project run much smoother.
upvoted 0 times
...
Kristin
5 months ago
I agree, having WBS elements serve multiple purposes can really help in organizing a project effectively.
upvoted 0 times
...
Johnetta
5 months ago
Agreed, it's important to have the option to assign WBS elements to different project definitions for better organization.
upvoted 0 times
...
Nancey
6 months ago
Having multiple purposes for WBS elements can definitely make project management more efficient.
upvoted 0 times
...
Cassandra
6 months ago
I think A, C, and D are correct too. It's great to have that flexibility in creating WBS elements.
upvoted 0 times
...
Deangelo
6 months ago
I think A, C, and D are correct too. It's great to have that flexibility in creating WBS elements.
upvoted 0 times
...
...
Catarina
6 months ago
Right, and E was fine because the structure can have several top-level WBS elements.
upvoted 0 times
...
Stephaine
6 months ago
Yeah, I avoided B too. D made sense since a WBS element can serve multiple functions.
upvoted 0 times
...
Gerry
6 months ago
But wasn't B misleading? It said up to 10 levels.
upvoted 0 times
...
Isaac
6 months ago
Same here. A was clear because you can create several WBS elements per level.
upvoted 0 times
...
Lachelle
6 months ago
B is definitely wrong. There's no limit on the number of levels in a WBS. E is also incorrect - there can be more than one level 1 element.
upvoted 0 times
Layla
5 months ago
D) WBS element can be a planning element, an account assignment element, and a billing element at the same time.
upvoted 0 times
...
Doyle
5 months ago
C) A WBS element of the new project can be assigned to a different project definition.
upvoted 0 times
...
Maryanne
5 months ago
C) A WBS element of the new project can be assigned to a different project definition.
upvoted 0 times
...
Aleshia
5 months ago
A) You can create several WBS elements per level.
upvoted 0 times
...
Doyle
6 months ago
A) You can create several WBS elements per level.
upvoted 0 times
...
Sheridan
6 months ago
C) A WBS element of the new project can be assigned to a different project definition.
upvoted 0 times
...
Sheridan
6 months ago
A) You can create several WBS elements per level.
upvoted 0 times
...
...
Catarina
7 months ago
Agreed. I picked A, D, and E as my answers.
upvoted 0 times
...
Isaac
7 months ago
I found it straightforward, but some options were confusing.
upvoted 0 times
...
Gerry
7 months ago
It was tricky. Had to think a lot.
upvoted 0 times
...
Wynell
7 months ago
I think A, C, and D are correct. Creating multiple WBS elements per level makes sense for complex projects. And being able to assign a WBS element to multiple projects is a useful feature.
upvoted 0 times
...
Catarina
7 months ago
How did you feel about the WBS element question in the exam?
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77