Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS412_2021 Topic 7 Question 37 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 37
Topic #: 7
[All C_TS412_2021 Questions]

Resources

How can you define external task in your project.

Note : there are 2 correct answers for this question.

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Brock
17 days ago
Haha, I'm going to go with B and D. Who needs purchase orders and service milestones when you can just create activities in your network? That's the way to do it!
upvoted 0 times
...
Lenna
23 days ago
I think creating a service milestone and activity might be considered external tasks in a project.
upvoted 0 times
...
Allene
24 days ago
I'm not sure, I think it could also be C and D.
upvoted 0 times
...
Shawn
1 months ago
I agree with Vi, assigning a purchase order and creating an external activity make sense.
upvoted 0 times
...
Vanesa
1 months ago
I agree with Alona. B and D are the right options. Assigning a purchase order and creating a service milestone don't seem to be the way to define an external task.
upvoted 0 times
...
Vi
1 months ago
I think the correct answers are A and B.
upvoted 0 times
...
Alona
1 months ago
B and D seem like the correct answers to me. Creating an external activity in a network and a service activity in a network are the ways to define an external task.
upvoted 0 times
Berry
14 days ago
So, B and D are the correct options for defining external tasks in a project.
upvoted 0 times
...
Coral
17 days ago
Assigning a purchase order and creating a service milestone are not ways to define external tasks.
upvoted 0 times
...
Jutta
18 days ago
Yes, creating an external activity in a network and a service activity in a network define external tasks.
upvoted 0 times
...
Peggie
28 days ago
I think B and D are the correct answers.
upvoted 0 times
...
Jerlene
1 months ago
Yes, creating an external activity in a network and a service activity in a network are the correct ways to define an external task.
upvoted 0 times
...
Jerlene
1 months ago
I agree, B and D are the correct answers. Those are the ways to define an external task.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77