Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS422_2022 Topic 1 Question 1 Discussion

Actual exam question for SAP's C_TS422_2022 exam
Question #: 1
Topic #: 1
[All C_TS422_2022 Questions]

For a production version to be valid and consistent, what requirements must be fulfilled? Note: There are 3 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: A, B, C

Contribute your Thoughts:

Torie
5 months ago
Haha, I bet the person who came up with option E was feeling pretty clever. But A, C, and D are the real deal.
upvoted 0 times
Andra
4 months ago
It's important to make sure the deletion flag is not set, the routing and BOM are valid, and the routing is a rate routing.
upvoted 0 times
...
Kelvin
4 months ago
Definitely, but A, C, and D are the key requirements for a valid and consistent production version.
upvoted 0 times
...
Emeline
4 months ago
I agree, option E does seem like a tricky one.
upvoted 0 times
...
...
Belen
5 months ago
This is a classic 'select all that apply' question. A, C, and D are the way to go. E is just a silly distractor.
upvoted 0 times
...
Evangelina
5 months ago
Hmm, I'm not sure about B. The lot size range seems like an optional requirement, not a must-have. A, C, and D are the clear winners here.
upvoted 0 times
Dorothy
4 months ago
User 3: I agree with Dorothy, B might be important but A, C, and D are definitely must-haves.
upvoted 0 times
...
Penney
4 months ago
User 2: I disagree, A, C, and D are the key requirements for a valid and consistent production version.
upvoted 0 times
...
Jesus
4 months ago
User 1: I think B is important because it ensures the lot size range matches the assigned routing.
upvoted 0 times
...
...
Pearly
5 months ago
Definitely agree with A, C, and D. The lot size range is a tricky one, but the validity period and rate routing are crucial.
upvoted 0 times
Ernest
4 months ago
User 2
upvoted 0 times
...
Annice
4 months ago
User 1
upvoted 0 times
...
Cathrine
4 months ago
D) The assigned routing must be a rate routing.
upvoted 0 times
...
Domingo
5 months ago
C) The assigned routing and bill of material (BOM) must be valid in the entire validity period.
upvoted 0 times
...
Whitney
5 months ago
A) The deletion flag must NOT be set for the bill of material (BOM) or the routing
upvoted 0 times
...
...
Onita
5 months ago
I think A, C, and D are the correct answers. The production version needs to have a valid BOM and routing, and the routing must be a rate routing.
upvoted 0 times
Brunilda
4 months ago
I appreciate it, have a great day!
upvoted 0 times
...
Sabrina
4 months ago
No problem, happy to help.
upvoted 0 times
...
Luis
4 months ago
Got it, thanks for clarifying.
upvoted 0 times
...
Wilbert
4 months ago
Actually, the lot size range must be within the lot size range of the assigned routing for the production version to be valid and consistent.
upvoted 0 times
...
Lynette
4 months ago
So, the lot size range doesn't matter for the production version?
upvoted 0 times
...
Yun
4 months ago
Yes, you are correct. The deletion flag must NOT be set for the BOM or routing, the assigned BOM and routing must be valid in the entire validity period, and the routing must be a rate routing.
upvoted 0 times
...
Barb
5 months ago
Yes, and the assigned routing and BOM must be valid in the entire validity period.
upvoted 0 times
...
Temeka
5 months ago
I agree, the deletion flag must NOT be set for the BOM or routing.
upvoted 0 times
...
Filiberto
5 months ago
I think A, C, and D are the correct answers.
upvoted 0 times
...
...

Save Cancel