Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS422_2022 Topic 10 Question 27 Discussion

Actual exam question for SAP's C_TS422_2022 exam
Question #: 27
Topic #: 10
[All C_TS422_2022 Questions]

What could be the reason for multiple commitments, where several operations have the same scheduled dates on a work center after dispatching?

Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: A, B

Contribute your Thoughts:

Izetta
21 days ago
I also think it could be because the work center has several individual capacities.
upvoted 0 times
...
Nicolette
27 days ago
I agree with Tayna, that could definitely cause multiple commitments.
upvoted 0 times
...
Tayna
1 months ago
I think the reason could be that the Finite Scheduling indicator is NOT set.
upvoted 0 times
...
Mila
1 months ago
If the Finite Scheduling indicator is off, that's just asking for trouble. Might as well schedule everything on a dartboard at that point. *laughs*
upvoted 0 times
...
Natalie
1 months ago
Wait, so we're supposed to pick two correct answers? This is like trying to hit a moving target with a blindfold on. *chuckles*
upvoted 0 times
Kasandra
1 hours ago
D) Alternative work centers are fully occupied.
upvoted 0 times
...
Wynell
6 days ago
C) The Change Planning Direction indicator is set in the strategy profile
upvoted 0 times
...
Blondell
9 days ago
B) The work center has several individual capacities
upvoted 0 times
...
Xenia
11 days ago
A) The Finite Scheduling indicator is NOT set in the strategy profile.
upvoted 0 times
...
...
Francesco
1 months ago
Multiple capacities on the work center, huh? That's a clever one. I bet that could lead to some real scheduling headaches.
upvoted 0 times
...
Earleen
1 months ago
Hmm, I think the Finite Scheduling indicator being off could definitely cause this issue. But those alternative work centers being occupied also sounds plausible.
upvoted 0 times
Gene
27 days ago
I agree, the Finite Scheduling indicator being off could definitely cause this issue.
upvoted 0 times
...
Gene
27 days ago
Yes, alternative work centers being fully occupied could also be a reason for multiple commitments.
upvoted 0 times
...
...
Brittni
1 months ago
Ah, the Change Planning Direction indicator being set in the strategy profile - that's an interesting one! I wouldn't have thought of that straight away.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77