SAP Exam C_TS422_2022 Topic 8 Question 25 Discussion

Actual exam question for SAP's C_TS422_2022 exam
Question #: 25
Topic #: 8
[All C_TS422_2022 Questions]

Your company produces a finished good based on a forecast and expects it to be in stock when customers order it. If customers order more than the forecasted quantity, this must NOT have any impact on the production program. Which planning strategy do you use?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Sharita
2 months ago
B) Planning with final assembly is the way to go. Gotta love those last-minute orders that keep us on our toes. It's like a surprise party, but with more spreadsheets!
upvoted 0 times
Marnie
22 days ago
C) Make-to-stock production (20)
upvoted 0 times
...
Kanisha
26 days ago
B) Planning with final assembly (40)
upvoted 0 times
...
Sabine
1 months ago
A) Make-to-stock production (10)
upvoted 0 times
...
...
Phung
2 months ago
I'm going with D) Planning without final assembly. Who needs a final assembly when you can just sell the raw materials, am I right? *wink wink*
upvoted 0 times
...
Bettina
2 months ago
But with make-to-stock production, the finished goods are produced based on forecasted demand, ensuring they are in stock when customers order.
upvoted 0 times
...
Ahmad
2 months ago
I disagree, I believe the correct answer is B) Planning with final assembly.
upvoted 0 times
...
Luis
2 months ago
C) Make-to-stock production sounds like the right choice. Keeping the goods in stock and ready to ship is the best way to handle unexpected orders.
upvoted 0 times
Lavonda
1 months ago
C) Make-to-stock production (20)
upvoted 0 times
...
An
2 months ago
B) Planning with final assembly (40)
upvoted 0 times
...
Anthony
2 months ago
A) Make-to-stock production (10)
upvoted 0 times
...
...
Alease
2 months ago
I think the answer is B) Planning with final assembly. It's the only one that says the production program won't be impacted if customers order more than the forecast.
upvoted 0 times
Elouise
1 months ago
A) Make-to-stock production (10) could work too, as long as there is enough buffer stock to cover unexpected customer orders.
upvoted 0 times
...
Jerry
1 months ago
I see your point, but D) Planning without final assembly (50) may not be the best option if customer orders exceed the forecast.
upvoted 0 times
...
Bobbie
2 months ago
I think C) Make-to-stock production (20) could also work, as it focuses on having the finished goods in stock.
upvoted 0 times
...
Loise
2 months ago
I agree, B) Planning with final assembly is the best choice.
upvoted 0 times
...
...
Bettina
2 months ago
I think the answer is A) Make-to-stock production.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77