Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: C, D

Contribute your Thoughts:

Tony
2 months ago
B and D, no doubt. Although I have to say, 'float after production' sounds like a great way to spend a lazy afternoon. Maybe we could all take a break and do some floating after the exam?
upvoted 0 times
...
Carlota
2 months ago
B and D, definitely. Although I'm a bit worried about the 'float after production' option. Is that like a yoga pose or something?
upvoted 0 times
Darrin
1 months ago
I'm pretty sure it's not a yoga pose, but I'm not entirely sure what it means either.
upvoted 0 times
...
Rosalind
1 months ago
Yeah, I agree. 'Float after production' does sound a bit confusing.
upvoted 0 times
...
Darell
1 months ago
I think B and D are the correct time elements for lead time scheduling.
upvoted 0 times
...
...
Lorenza
2 months ago
This is easy! B and D are the correct answers. I mean, come on, how could you not know that? It's Production 101.
upvoted 0 times
...
Mitzie
2 months ago
Hmm, I'd say B and D are the key ones. Setup time is crucial, and total replenishment lead time is a no-brainer. The other options are just fluff.
upvoted 0 times
Huey
1 months ago
Opening period and float after production are not as relevant compared to setup time and total replenishment lead time.
upvoted 0 times
...
Ronald
1 months ago
Total replenishment lead time is crucial for planning production orders.
upvoted 0 times
...
Bette
2 months ago
I agree, setup time is definitely important for lead time scheduling.
upvoted 0 times
...
...
Carey
2 months ago
I believe Total replenishment lead time and Float after production are also important factors to consider.
upvoted 0 times
...
Colton
2 months ago
B and D for sure. Who cares about opening periods and floats? I just want to get the order done on time!
upvoted 0 times
Lynna
2 months ago
It's true that B and D are crucial, but all time elements play a role in ensuring orders are completed on time.
upvoted 0 times
...
Cristy
2 months ago
Opening periods and floats might not seem important, but they can impact the overall production schedule.
upvoted 0 times
...
Leonor
2 months ago
I agree, B and D are the most important time elements for lead time scheduling.
upvoted 0 times
...
...
Crissy
3 months ago
I agree with Yuette. Opening period and Setup time are crucial for lead time scheduling.
upvoted 0 times
...
Yuette
3 months ago
I think the relevant time elements are Opening period and Setup time.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77