Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS422_2023 Topic 2 Question 16 Discussion

Actual exam question for SAP's C_TS422_2023 exam
Question #: 16
Topic #: 2
[All C_TS422_2023 Questions]

Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: C, D

Contribute your Thoughts:

Tony
11 days ago
B and D, no doubt. Although I have to say, 'float after production' sounds like a great way to spend a lazy afternoon. Maybe we could all take a break and do some floating after the exam?
upvoted 0 times
...
Carlota
12 days ago
B and D, definitely. Although I'm a bit worried about the 'float after production' option. Is that like a yoga pose or something?
upvoted 0 times
...
Lorenza
15 days ago
This is easy! B and D are the correct answers. I mean, come on, how could you not know that? It's Production 101.
upvoted 0 times
...
Mitzie
16 days ago
Hmm, I'd say B and D are the key ones. Setup time is crucial, and total replenishment lead time is a no-brainer. The other options are just fluff.
upvoted 0 times
Ronald
6 hours ago
Total replenishment lead time is crucial for planning production orders.
upvoted 0 times
...
Bette
3 days ago
I agree, setup time is definitely important for lead time scheduling.
upvoted 0 times
...
...
Carey
29 days ago
I believe Total replenishment lead time and Float after production are also important factors to consider.
upvoted 0 times
...
Colton
29 days ago
B and D for sure. Who cares about opening periods and floats? I just want to get the order done on time!
upvoted 0 times
Lynna
10 days ago
It's true that B and D are crucial, but all time elements play a role in ensuring orders are completed on time.
upvoted 0 times
...
Cristy
15 days ago
Opening periods and floats might not seem important, but they can impact the overall production schedule.
upvoted 0 times
...
Leonor
24 days ago
I agree, B and D are the most important time elements for lead time scheduling.
upvoted 0 times
...
...
Crissy
1 months ago
I agree with Yuette. Opening period and Setup time are crucial for lead time scheduling.
upvoted 0 times
...
Yuette
1 months ago
I think the relevant time elements are Opening period and Setup time.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77