Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS4CO_2021 Topic 8 Question 52 Discussion

Actual exam question for SAP's C_TS4CO_2021 exam
Question #: 52
Topic #: 8
[All C_TS4CO_2021 Questions]

You want to use budget availability control for your projects and internal orders. What can you check using budget availability control? Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: B, C

Contribute your Thoughts:

Amber
2 months ago
I believe we can also check the availability of funds according to tolerance limits. It's crucial to stay within budget constraints.
upvoted 0 times
...
Annice
2 months ago
This question is as clear as mud. I'm going to go with A, B, and C. Who needs object currency when you can just throw money at the problem?
upvoted 0 times
Suzi
1 months ago
User 3: Object currency is important too, we can't ignore that.
upvoted 0 times
...
Fanny
1 months ago
Yeah, that sounds like a good idea. We should also consider the tolerance limits.
upvoted 0 times
...
Phuong
2 months ago
I think we should check the availability of funds using overall plan value.
upvoted 0 times
...
...
Carlene
2 months ago
I agree with Justa. It's important to have an overview of the funds for the project.
upvoted 0 times
...
Leah
2 months ago
Ah, the age-old question of 'where's the money?' B and D, for sure. Gotta keep an eye on those tolerance limits and the period-level availability.
upvoted 0 times
Fatima
26 days ago
Absolutely, keeping track of those will help ensure financial control.
upvoted 0 times
...
Luis
27 days ago
Agreed, those are important factors to consider when managing budgets.
upvoted 0 times
...
Dorathy
1 months ago
Definitely B and D. Tolerance limits and period-level availability are key.
upvoted 0 times
...
Lavonna
1 months ago
D) The availability of funds on period level
upvoted 0 times
...
Sarah
1 months ago
C) The availability of funds in object currency
upvoted 0 times
...
Wilburn
2 months ago
B) The availability of funds according to tolerance limits
upvoted 0 times
...
Stefanie
2 months ago
A) The availability of funds using overall plan value
upvoted 0 times
...
...
Noel
2 months ago
D? Really? Who cares about the availability of funds on a period level? That's just overkill for budget control. A and B all the way!
upvoted 0 times
...
Justa
3 months ago
I think we can check the availability of funds using overall plan value.
upvoted 0 times
...
Selma
3 months ago
Hmm, I think C is also a correct answer. We need to check the availability of funds in the object currency, not just the overall plan.
upvoted 0 times
Shawna
2 months ago
I think C is also a correct answer. We need to check the availability of funds in the object currency, not just the overall plan.
upvoted 0 times
...
Jenifer
2 months ago
D) The availability of funds on period level
upvoted 0 times
...
Lashandra
2 months ago
C) The availability of funds in object currency
upvoted 0 times
...
Ty
2 months ago
B) The availability of funds according to tolerance limits
upvoted 0 times
...
Mireya
2 months ago
A) The availability of funds using overall plan value
upvoted 0 times
...
...
Jeannetta
3 months ago
I'm pretty sure the correct answers are A and B. Checking the overall plan value and tolerance limits are essential for budget availability control.
upvoted 0 times
Jina
2 months ago
Definitely, it's crucial to have a clear understanding of the funds available for projects and internal orders.
upvoted 0 times
...
Teresita
2 months ago
That makes sense, those are important factors to consider for budget availability control.
upvoted 0 times
...
Leota
2 months ago
Yes, we need to check the availability of funds using overall plan value and according to tolerance limits.
upvoted 0 times
...
Floyd
2 months ago
I think you're right, A and B are the correct answers.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77