SAP Exam E_S4HCON2023 Topic 5 Question 30 Discussion

Actual exam question for SAP's E_S4HCON2023 exam
Question #: 30
Topic #: 5
[All E_S4HCON2023 Questions]

You are performing an SAP S/4HANA conversion with DMO. You are using the downtime-optimized data conversion (DoC). Which steps can partially be moved to uptime processing? Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: B, D

Contribute your Thoughts:

Johanna
2 months ago
I'm feeling pretty confident about this one. The conversion and main import steps can be partially moved to uptime processing, while the software update and migration steps have to be done during downtime. Nailed it!
upvoted 0 times
...
Evette
2 months ago
Hey, I heard that the DMO process is like a rollercoaster ride - lots of twists and turns, but if you hold on tight, you'll make it through! As for the question, I'm going with B and C. Sounds about right to me.
upvoted 0 times
Arlette
1 months ago
Good choice, the DMO process can be a wild ride but it's manageable.
upvoted 0 times
...
Johnetta
1 months ago
Yeah, those steps can be moved to uptime processing.
upvoted 0 times
...
Dierdre
2 months ago
I think B and C are the correct answers.
upvoted 0 times
...
...
Virgie
2 months ago
I believe D) Migration can also be partially moved to uptime processing to optimize the conversion process.
upvoted 0 times
...
Jennifer
2 months ago
Hmm, I'm not too sure about this one. But I do know that the software update and migration steps can't be moved to uptime processing. Definitely need to double-check the correct answers.
upvoted 0 times
...
Alfreda
2 months ago
I think the answer is B and C. The conversion step and the main import can partially be moved to uptime processing, right?
upvoted 0 times
Mitsue
1 months ago
Agreed. It's great that there are options like downtime-optimized data conversion to help with that.
upvoted 0 times
...
Roosevelt
2 months ago
Definitely, it's important to optimize the process to minimize disruption to business operations.
upvoted 0 times
...
Marjory
2 months ago
Exactly, the conversion and main import steps can be optimized for uptime processing during the SAP S/4HANA conversion with DMO.
upvoted 0 times
...
Joanna
2 months ago
That's good to know. It helps reduce downtime during the SAP S/4HANA conversion.
upvoted 0 times
...
Shaun
2 months ago
Yes, you are correct. The conversion step and the main import can be moved to uptime processing.
upvoted 0 times
...
Lashandra
2 months ago
That's right. Those are the two steps that can be partially moved to uptime processing.
upvoted 0 times
...
Isreal
2 months ago
Yes, you are correct. The conversion and main import steps can be moved to uptime processing.
upvoted 0 times
...
...
Desire
3 months ago
I agree with Lenny. Software update can be done during uptime to reduce downtime.
upvoted 0 times
...
Lenny
3 months ago
I think A) Software update can be moved to uptime processing.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77