Scaled Agile Exam SAFe-APM Topic 2 Question 18 Discussion

Actual exam question for Scaled Agile's SAFe-APM exam
Question #: 18
Topic #: 2
[All SAFe-APM Questions]

Which item on the ART planning board might indicate a market window occurrence during a PI?

Show Suggested Answer Hide Answer
Suggested Answer: B

A milestone is a specific point in time that marks a significant event or achievement for the ART or Solution Train. A milestone can indicate a market window occurrence during a PI, which is a limited period of time in which a product or service can be launched to gain a competitive advantage or meet a customer demand. A milestone can help the ART or Solution Train align their delivery with the market window, and communicate their progress and readiness to the stakeholders.


Milestones: This article from the Scaled Agile Framework explains the concept and purpose of milestones, and describes the four types of milestones: Program Increment (PI), Fixed-Date, Learning, and Benefits.

ART Planning Board: This article from the Scaled Agile Framework describes the role and structure of the ART Planning Board, and how it supports the PI Planning process and the Program Board.

ART Planning Board - PI Planning: This article from Ivar Jacobson International provides practical advice and examples of how to use the ART Planning Board during the Management Review, and what to look for in terms of market windows, dependencies, risks, and objectives.

Contribute your Thoughts:

Taryn
2 months ago
I think Business value is important too, as it can help prioritize features based on market demand.
upvoted 0 times
...
Tamekia
2 months ago
I believe it could also be Dependencies, as they can impact the timing of the market window.
upvoted 0 times
...
Lonna
2 months ago
Well, well, looks like we've got a bunch of market window experts here. I'm just impressed you all know what an ART planning board is. Bravo!
upvoted 0 times
Adolph
1 months ago
D) Business value
upvoted 0 times
...
Layla
1 months ago
C) Dependencies
upvoted 0 times
...
Velda
2 months ago
B) Milestone
upvoted 0 times
...
Vallie
2 months ago
A) Feature
upvoted 0 times
...
...
Giovanna
2 months ago
Ah, the age-old question: which item on the ART planning board is most likely to give you a heart attack during a PI? I'm putting my money on all of them!
upvoted 0 times
...
Garry
3 months ago
A) Feature? Really? Might as well ask which item on the menu indicates how hungry I am. Sheesh.
upvoted 0 times
...
Paris
3 months ago
Hold up, you guys are overthinking this. The answer is clearly D) Business value. That's where the real money is, baby!
upvoted 0 times
Gussie
1 months ago
Let's not forget about C) Dependencies, they play a big role in market timing.
upvoted 0 times
...
Twana
1 months ago
I agree, focusing on the business value is crucial for success in the market.
upvoted 0 times
...
Alease
1 months ago
I agree with the user comment, it's D) Business value for sure.
upvoted 0 times
...
Rodney
1 months ago
You're right, D) Business value is the key indicator for market window occurrence.
upvoted 0 times
...
Franklyn
1 months ago
D) Business value
upvoted 0 times
...
Alysa
2 months ago
C) Dependencies
upvoted 0 times
...
Sarah
2 months ago
B) Milestone
upvoted 0 times
...
Deandrea
2 months ago
No way, it's definitely B) Milestone, that's when we know we're on track.
upvoted 0 times
...
Whitney
2 months ago
A) Feature
upvoted 0 times
...
Alishia
3 months ago
I think it's A) Feature, that's what drives the market.
upvoted 0 times
...
...
Sabine
3 months ago
I think the correct answer is B) Milestone. That's where you'd see any market windows during a PI.
upvoted 0 times
Luis
2 months ago
Definitely, it's important to track them during a PI.
upvoted 0 times
...
Jin
3 months ago
I agree, Milestones are key indicators of market windows.
upvoted 0 times
...
...
Wilda
3 months ago
Nah, B) Milestone? That's way too obvious. I'm going with C) Dependencies. Gotta watch out for those pesky external factors, am I right?
upvoted 0 times
...
Vallie
3 months ago
I agree with Eliz, Milestone is a key indicator of progress.
upvoted 0 times
...
Eliz
3 months ago
I think it's Milestone because it shows progress towards a goal.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77