Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Scaled Agile Exam SAFe-RTE Topic 1 Question 32 Discussion

Actual exam question for Scaled Agile's SAFe-RTE exam
Question #: 32
Topic #: 1
[All SAFe-RTE Questions]

Which activity takes place during Team Breakout #2 on the second day of Program In-crement (PI) Planning?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Alfred
5 months ago
Ah, the joys of PI Planning. It's like a game of Tetris, but with more spreadsheets and less falling blocks. I bet the RTE wishes they had a 'Pause' button sometimes.
upvoted 0 times
...
Pok
5 months ago
I feel like the answer is hidden in plain sight, like a secret passageway in a cartoon mansion. Maybe the key is to think outside the box?
upvoted 0 times
Chery
5 months ago
Maybe we should consider how the Release Train Engineer combines all Team PI Objectives into Program PI Objectives.
upvoted 0 times
...
Chery
5 months ago
I think the key is to focus on visualizing all Feature delivery and dependencies on the program board.
upvoted 0 times
...
...
Tiera
6 months ago
A seems right to me. The RTE has to make sure the schedule is still working after all the team discussions. Kinda like a train conductor checking the timetable.
upvoted 0 times
...
Cherelle
6 months ago
D is my pick. The RTE has to consolidate all the team-level objectives into program-level ones. Gotta keep that train running on time!
upvoted 0 times
Shenika
5 months ago
Yes, that's right. It helps ensure alignment and coordination across all the teams on the Agile Release Train.
upvoted 0 times
...
Kanisha
5 months ago
I agree, D is the correct option. It's important for the RTE to combine all the objectives for the program.
upvoted 0 times
...
...
Shenika
6 months ago
Hmm, I'm not sure about this one. Maybe B? Sounds like something the Business Owners would do to speed things up.
upvoted 0 times
Cordelia
5 months ago
Hmm, I'm not sure about this one. Maybe B? Sounds like something the Business Owners would do to speed things up.
upvoted 0 times
...
Ellsworth
5 months ago
B) Business Owners assign business value without team discussion so they can normalize business value across all teams on the Agile Release Train
upvoted 0 times
...
Inocencia
5 months ago
Actually, it's D. The RTE combines all Team PI Objectives into Program PI Objectives during Team Breakout #2.
upvoted 0 times
...
Rosalia
5 months ago
I agree, C makes sense to ensure everyone is on the same page with dependencies.
upvoted 0 times
...
Annamae
5 months ago
I think it's C, visualizing all Feature delivery and dependencies on the program board is crucial.
upvoted 0 times
...
Theola
5 months ago
A) The RTE modifies the PI Iteration schedule, if needed, based on the scope of high priority Features
upvoted 0 times
...
...
Vicki
6 months ago
I agree with Xuan, C makes the most sense for Team Breakout #2 during PI Planning.
upvoted 0 times
...
Zona
6 months ago
I think the correct answer is C. The program board is used to visualize all Feature delivery and dependencies during Team Breakout #2.
upvoted 0 times
Gabriele
6 months ago
Yes, it helps ensure that everyone is on the same page and can see the big picture.
upvoted 0 times
...
Clay
6 months ago
Yes, it helps ensure that everyone is on the same page and can see the big picture.
upvoted 0 times
...
Jackie
6 months ago
I agree, the program board is crucial for visualizing all Feature delivery and dependencies.
upvoted 0 times
...
Coletta
6 months ago
I agree, the program board is essential for visualizing all Feature delivery and dependencies.
upvoted 0 times
...
...
Xuan
6 months ago
I think the answer is C because it's important to visualize all feature delivery and dependencies.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77