An Agile Team decides they want to use pair programming in future Iterations. Where should this be captured?
The decision to implement pair programming in future iterations is a team-level improvement action that stems from reflecting on their current processes and identifying areas for enhancement. This is best captured during the team's retrospective:
Retrospective Purpose: The retrospective is a regular meeting where the team reflects on what went well, what didn't, and what could be improved.
Action Items: Decisions and action items, such as adopting pair programming, are documented in the retrospective notes to ensure they are followed up in future iterations.
Continuous Improvement: Capturing this in the retrospective notes ensures the team is committed to continuous improvement and has a clear record of their decisions and plans for process enhancements.
SAFe Scrum Master Reference:
SAFe Advanced Scrum Master Training Material, Chapter on Team Retrospectives.
Becky
3 months agoLottie
3 months agoMartha
3 months agoCasie
3 months agoJustine
3 months agoMyong
2 months agoKanisha
2 months agoFabiola
3 months agoYun
4 months agoChanel
2 months agoKimberely
3 months agoStevie
3 months agoIvan
3 months agoChandra
4 months agoZena
4 months agoShawna
3 months agoHelga
4 months agoViva
4 months agoVallie
4 months agoDanica
3 months agoKristian
3 months agoJaney
3 months agoHenriette
4 months agoOzell
4 months agoDalene
3 months agoJacob
4 months agoBrice
4 months agoSuzi
4 months ago