Scaled Agile Exam SAFe-SGP Topic 5 Question 25 Discussion

Actual exam question for Scaled Agile's SAFe-SGP exam
Question #: 25
Topic #: 5
[All SAFe-SGP Questions]

When do organizations begin realizing better results when following the Implementation Roadmap?

Show Suggested Answer Hide Answer
Suggested Answer: B

According to theImplementation Roadmaparticle on the Scaled Agile Framework website, organizations begin realizing better results when following the Implementation Roadmap as soon as the first Program Increment (PI). The article states that ''The first PI is a critical milestone. It's the first time the new ART delivers a fully integrated and tested increment of value. It's also the first time the ART demonstrates its new way of working to the enterprise and its stakeholders. The first PI is a big deal. It's a celebration of the new culture and the new way of working. It's also the first time the enterprise can see the benefits of the new approach.'' Therefore, the correct answer is B, as soon as the first Program Increment. The other options are not accurate, as the roadmap consists of more than just steps, training, or metrics. It is a continuous journey of learning and improvement.


Contribute your Thoughts:

Myong
2 days ago
Predictability measure over 80%? Sounds like someone's been drinking the Agile Kool-Aid a little too much. I'll take B, thank you very much.
upvoted 0 times
...
Lizette
6 days ago
I think it's actually once the predictability measure exceeds 80%. That's when you can really see the impact of following the Implementation Roadmap.
upvoted 0 times
...
Aretha
10 days ago
I agree with Earlean. It makes sense that results would improve as soon as the first milestone is reached.
upvoted 0 times
...
Rashida
14 days ago
Hah, training classes? Who needs those? I'm going with B. As soon as that first Program Increment hits, it's party time!
upvoted 0 times
Callie
2 days ago
User 1: Who needs training classes? I'm going with B. As soon as that first Program Increment hits, it's party time!
upvoted 0 times
...
...
Earlean
18 days ago
I think organizations start seeing better results after the first Program Increment.
upvoted 0 times
...
Rolf
19 days ago
A all the way! It's not rocket science - you follow the whole roadmap, then you get the results. Simple as that.
upvoted 0 times
Wilbert
1 days ago
B) As soon as the first Program Increment
upvoted 0 times
...
Paola
5 days ago
A) Once all steps in the roadmap are complete
upvoted 0 times
...
...
Herman
24 days ago
I'm going with C. Gotta make sure everyone's trained up before you can expect any real results, am I right?
upvoted 0 times
...
Enola
25 days ago
D sounds good to me. Once the predictability measure exceeds 80%, that's when you know the organization is on the right track.
upvoted 0 times
...
James
26 days ago
I think the answer is B. As soon as the first Program Increment. Why wait for the whole roadmap when you can start seeing results right away?
upvoted 0 times
Lorean
11 days ago
That's a good point, it's all about finding the right balance between quick wins and long-term success.
upvoted 0 times
...
Felix
15 days ago
True, but sometimes getting quick wins can help build momentum for the rest of the roadmap.
upvoted 0 times
...
Stefan
17 days ago
But wouldn't it be better to ensure all steps are complete for a more comprehensive outcome?
upvoted 0 times
...
Felicitas
19 days ago
I agree with you, starting to see results early on can be motivating.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77