Scrum Exam SPS Topic 1 Question 12 Discussion

Actual exam question for Scrum's Scaled Professional Scrum exam
Question #: 12
Topic #: 1
[All Scaled Professional Scrum Questions]

During Cross-Team Refinement, the ordered Product Backlog (1 through 9) is mapped out so

the Nexus can visualize dependencies. For example, PBI 5 for Team Orange is dependent on

Team Red completing PBI 1.

All else being equal, which PBI is most concerning?

(choose the best answer)

Show Suggested Answer Hide Answer
Suggested Answer: D

PBI 2 is the most concerning because it involves a cross-team dependency within the same Sprint, which can create challenges and risks for the integration and delivery of the product increment. According to the Online Nexus Guide1, dependencies should be minimized or eliminated as much as possible, and if they exist, they should be made transparent and resolved as early as possible. Cross-team dependencies within the same Sprint can cause delays, conflicts, rework, and waste, and reduce the quality and value of the product increment 234.

The other answers are not correct for the following reasons:

A . PBI 2, because it has the most dependencies. This answer is not accurate because PBI 2 does not have the most dependencies, but only one dependency with PBI 1 from Team Red. PBI 3 has the most dependencies, as it depends on PBI 1, PBI 2, and PBI 4. However, PBI 3 is not as concerning as PBI 2, because its dependencies are not within the same Sprint, but across different Sprints. This means that PBI 3 can be refined and planned in advance, and the teams can coordinate and communicate their work more effectively 5.

B . PBI 1, because it is on the top of the Product Backlog. This answer is not relevant because the position of PBI 1 on the Product Backlog does not indicate its level of concern, but its priority and value. The Product Backlog is ordered by the Product Owner based on various factors, such as business value, risk, complexity, and dependencies. PBI 1 may be on the top of the Product Backlog because it is the most valuable or urgent item, or because it is a prerequisite for other items, but it is not necessarily the most concerning item 6.

C . PBI 1, because it is the first piece of work with a dependency. This answer is not true because PBI 1 is not the first piece of work with a dependency, but the first piece of work that other items depend on. PBI 1 does not have any dependencies itself, but it creates dependencies for PBI 2, PBI 3, and PBI 5. Therefore, PBI 1 is not as concerning as PBI 2, because it does not depend on any other item, and it can be completed independently by Team Red 5.


Contribute your Thoughts:

Margot
23 hours ago
PBI 1 for sure. It's like the foundation of the whole thing. If that goes down, the whole Nexus is in trouble.
upvoted 0 times
...
Jerry
4 days ago
Haha, it's like a game of Jenga up in here! All these dependencies, who knows when the whole thing is gonna come crashing down.
upvoted 0 times
...
Larae
5 days ago
I think PBI 2 is the most concerning, since it has the most dependencies. That's just asking for trouble, you know?
upvoted 0 times
...
Catalina
18 days ago
I agree with Fausto. PBI 1 being the first one with a dependency is the real issue here. Can't ignore that.
upvoted 0 times
Charlene
10 days ago
User 3: PBI 2 also seems concerning because it has dependencies with a different team in the same Sprint.
upvoted 0 times
...
Louvenia
11 days ago
User 2: Yeah, I agree. It sets the tone for the rest of the dependencies.
upvoted 0 times
...
Lynna
13 days ago
User 1: I think PBI 1 is the most concerning because it is the first piece of work with a dependency.
upvoted 0 times
...
...
Almeta
1 months ago
I believe PBI 2 is most concerning because it has dependencies with a different team within the same Sprint.
upvoted 0 times
...
Ettie
1 months ago
I agree with Sue, PBI 1 being the first piece of work with a dependency makes it more concerning.
upvoted 0 times
...
Fausto
1 months ago
PBI 1 is definitely the most concerning, since it's the first piece of work with a dependency. That seems like the biggest risk to me.
upvoted 0 times
Paz
20 days ago
Yeah, it's important to make sure Team Red completes PBI 1 on time for Team Orange to start their work.
upvoted 0 times
...
Shawnta
1 months ago
I agree, PBI 1 being the first piece of work with a dependency does seem risky.
upvoted 0 times
...
...
Sue
1 months ago
I think PBI 1 is most concerning because it is the first piece of work with a dependency.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77